Renault Megane E-Tech
Iconic

EV60 220ch optimum charge

Blanc Glacier
Initial delivery period of 5 months
Raphabubu had opted for the Renault Megane E-Tech on 30/09/2022. When purchasing, he was initially given a delivery date of 18/02/2023, equating to a five months delivery period.
A delivery delayed by 1 month
In Raphabubu's case, his Renault Megane E-Tech was delivered with a slight one month delay, on 20/03/2023. Although rare, this delay remained within a reasonable timeframe. Renault still managed well.
In fact, Raphabubu waited 6 months
Raphabubu ordered their Renault Megane E-Tech in France on 30/09/2022. At the time of their order, the initially announced delivery date was 18/02/2023, which was an initial delivery time of 5 months. In the end, Raphabubu took possession of the vehicle on 20/03/2023, which resulted in a waiting time of 6 months.
See the other Renault Megane E-Tech deliveries
on 15/03/2023
on 31/03/2023